Title: Request for Funding Wabamun Pier Surface Rehabilitation Proposed Motion That Council approve an amount up to $280,000.00 for the revitalization of the Wabamun Pier to be funded from County Facilities Restricted Surplus.
Attachments: 1. 1. Administrative Report
Title
Request for Funding Wabamun Pier Surface Rehabilitation

Proposed Motion
That Council approve an amount up to $280,000.00 for the revitalization of the Wabamun Pier to be funded from County Facilities Restricted Surplus.

Body
Administration Recommendation
Administration supports the proposed motion as presented.

Purpose
To fund the revitalization of the Wabamun Pier.

Summary
In 2024 an assessment was completed by ISL and the pier was determined to be structurally sound, however some sections of the decking where identified as being soft. A visual inspection of sections not covered by the matting shows some deterioration of the boards. The existing decking on the pier is estimated to be around 50 years old. Parkland County has reviewed the assessment and is recommending that the pier be revitalized in conjunction with the ongoing work at Waterfront Park area. The entire deck would be removed and replaced with new planks, the approach to the pier would be repaired and cleaned up to make it more accessible and the damaged bumpers along the pier would be repaired.The pier currently does not have a railing or curbing installed. An increase in fall risk was identified due to the lower lake levels, in some locations the height from pier to water surface is greater than 6 feet. A railing and curb will be installed along the perimeter of the pier and ladder access points will be maintained. Parkland County is investing in the revitalization of Wabamun’s waterfront area and revitalizing the pier would ensure that this asset is maintained as a Parkland County gem for years to come.

Historical Information:
2021- Parkland County assumed responsibility for this asset
2015 - Village of Wabamun replaced some of the deck boards and installed the rubber matting

Strategic Plan/Policy/Legal/Staff Implications:
Complete Communities: To ensure that County infrastructure meets the needs of residents, businesses, and industry.

Financial Impact:
Cost: $280,000.00