File #: BL 26-004    Version: 1 Name: Infrastructure Borrowing - Entwistle Wastewater Rehabilitation Highway 16 Forcemain Replacement
Type: Bylaw Status: Council Agenda
File created: 2/11/2026 In control: Council
On agenda: 2/24/2026 Final action: 2/24/2026
Title: Bylaw 2026-09 - Infrastructure Borrowing - Entwistle Wastewater Rehabilitation Highway 16 Forcemain Replacement Proposed Motion That Bylaw 2026-09 - receive first reading.
Attachments: 1. 1. Bylaw 2026-09 Wastewater Rehab Ent Hwy 16 Forcemain

Title

Bylaw 2026-09 - Infrastructure Borrowing - Entwistle Wastewater Rehabilitation Highway 16 Forcemain Replacement

 

Proposed Motion

That Bylaw 2026-09 - receive first reading.

 

Body

Administration Recommendation

Administration supports the proposed motion.

 

Purpose

In accordance with Sections 251 and 258 of the Municipal Government Act, Council is required by Bylaw to facilitate long-term borrowing of funds.

 

Summary

The project will include the removal/abandonment and replacement of the sanitary forcemain beneath Highway 16 and the CN Rail line.

 

Design was initiated in 2024 and continued into 2025 with construction scheduled for 2026.

 

The cost of the infrastructure is not to exceed $1,100,000 and will be accommodated by debt borrowing. The anticipated interest rate is to be determined but is not to exceed 10 percent over a term not to exceed 30-years, as outlined in Bylaw 2026-09.

 

The repayment of the indebtedness for infrastructure, plus any interest expenses, is to be funded by utility rate revenue, municipal taxes and/or restricted surplus funds.

 

Administration will use an authorized financial institution or Province of Alberta, to facilitate the debt borrowing needs.

 

Historical Information:

-2024 Budget - Funding of $50,000 was approved for the initial design of the Entwistle Wastewater Rehabilitation Highway 16 Forcemain Replacement project.

-2025 (RFD 25‑138) - An additional $50,000 was approved to advance and complete detailed design work.

-2026 Budget (APP 25‑087) - Capital funding of $1,000,000 was approved to proceed with construction of the project.

 

Strategic Plan/Policy/Legal/Staff Implications:

Municipal Government Act - Sections 251 and 258

 

Financial Impact:

Cost:   $1,000,000

Source of Funding:  Debt