Title
Bylaw 2026-09 - Infrastructure Borrowing - Entwistle Wastewater Rehabilitation Highway 16 Forcemain Replacement
Proposed Motion
That Bylaw 2026-09 - receive first reading.
Body
Administration Recommendation
Administration supports the proposed motion.
Purpose
In accordance with Sections 251 and 258 of the Municipal Government Act, Council is required by Bylaw to facilitate long-term borrowing of funds.
Summary
The project will include the removal/abandonment and replacement of the sanitary forcemain beneath Highway 16 and the CN Rail line.
Design was initiated in 2024 and continued into 2025 with construction scheduled for 2026.
The cost of the infrastructure is not to exceed $1,100,000 and will be accommodated by debt borrowing. The anticipated interest rate is to be determined but is not to exceed 10 percent over a term not to exceed 30-years, as outlined in Bylaw 2026-09.
The repayment of the indebtedness for infrastructure, plus any interest expenses, is to be funded by utility rate revenue, municipal taxes and/or restricted surplus funds.
Administration will use an authorized financial institution or Province of Alberta, to facilitate the debt borrowing needs.
Historical Information:
-2024 Budget - Funding of $50,000 was approved for the initial design of the Entwistle Wastewater Rehabilitation Highway 16 Forcemain Replacement project.
-2025 (RFD 25‑138) - An additional $50,000 was approved to advance and complete detailed design work.
-2026 Budget (APP 25‑087) - Capital funding of $1,000,000 was approved to proceed with construction of the project.
Strategic Plan/Policy/Legal/Staff Implications:
Municipal Government Act - Sections 251 and 258
Financial Impact:
Cost: $1,000,000
Source of Funding: Debt