File #: BL 25-003    Version: 1 Name: Acheson Industrial Area Structure Plan Amendment and Redistricting for S.W. 29-52-26-4 and Lot 1 and 2, Block 1, Plan 032 1486
Type: Bylaw Status: Second Reading
File created: 1/20/2025 In control: Council
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Bylaw 2025-05 - Proposed Amendment to the Acheson Industrial Area Structure Bylaw 2020-13 for S.W. 29-52-26-4 and Lot 1 and 2, Block 1, Plan 032 1486 Proposed Motions 1. That Bylaw 2025-05 receive first reading. 2. That a Public Hearing be scheduled for March 11, 2025, at 9:30 am in Council Chambers to hear public comment on Bylaw 2025-05.
Attachments: 1. 1. Administrative Report to Council Beacon Data Centre, 2. 2. Bylaw 2025-05/2025-06 Presentation, 3. 3. Bylaw 2025-05, 4. 4. Bylaw 2025-06, 5. 5. ASP Amendment Location Map, 6. 6. ASP-Map 6 - Future Land Use Concept 04dec2024, 7. 7. Map 8 - Transportation Network - Proposed Amendment, 8. 8. Bylaw 2025-06 Schedule A - Redistricting Map, 9. 9. Alberta Transportation Letter of Support, 10. 10. What We Heard Report
Related files: BL 25-007

Title

Bylaw 2025-05 - Proposed Amendment to the Acheson Industrial Area Structure Bylaw 2020-13 for S.W. 29-52-26-4 and Lot 1 and 2, Block 1, Plan 032 1486

 

Proposed Motions

1. That Bylaw 2025-05 receive first reading.

2. That a Public Hearing be scheduled for March 11, 2025, at 9:30 am in Council Chambers to hear public comment on Bylaw 2025-05.

 

 

Body

Administration Recommendation

Administration supports the proposed motions.

 

Purpose

The purpose of the proposed Acheson Industrial Area Structure Plan (ASP) amendment is to support future industrial development on the subject lands.

 

Summary

Bylaw 2025-05 proposes amendments to Map 6: Future Land Use Concept and Map 8 - Transportation Network of the Acheson Industrial ASP, redesignating the existing land use of “Constrained Lands”. The designation of the lands described as S.W. 29-52-26-4 and Lot 1 and 2, Block 1, Plan 032 1486 is proposed to be amended to 'Commercial/Light Industrial'.

 

Historical Information:

N/A

 

Strategic Plan/Policy/Legal/Staff Implications:

Proposed Bylaw 2025-05 is consistent with the goals of the Municipal Development Plan No. 2017-14, the Acheson Industrial Area Structure Plan 2020-13, the Parkland County Strategic Plan 2022-2025, and is in alignment with the Edmonton Metropolitan Region Growth Plan.

 

Financial Impact:

Cost:0.00