File #: RFD 21-181    Version: 1 Name: Magnolia Community League, Sustainability Grant - Major Capital Request
Type: Request For Decision Status: Carried
File created: 9/16/2021 In control: Council
On agenda: 9/28/2021 Final action: 9/28/2021
Title: Magnolia Community League Sustainability Grant - Major Capital Request Proposed Motion That Council approve the Magnolia Community Club Sustainability Grant - Major Capital request in the amount of $25,000 to be included in the 2022 budget, as presented.
Attachments: 1. 1. Administrative Report, 2. 2. Application Form

Title

Magnolia Community League Sustainability Grant - Major Capital Request

 

Proposed Motion

That Council approve the Magnolia Community Club Sustainability Grant - Major Capital request in the amount of $25,000 to be included in the 2022 budget, as presented.

 

Body

Administration Recommendation

Administration supports the Magnolia Community Club request. These projects were identified as part of the 2019 Facility Condition Assessment Report, and will improve the hall's usability and attractiveness for renters.

 

Purpose

As per Policy C-RP03, requests submitted under the Sustainability Grant - Major Capital are to be approved by Council.

 

Summary

Magnolia Community Club is an active community league, hosting many events both outdoor and indoors.  The hall was built in 1973 and an addition was added in 1985.  Although the hall is in reasonably good shape, the Expected Useful Life (EUL) of many of the components of the hall is nearing the end of its life span. As part of the boards commitment to maintaining and extending the life span of the building, they have planned a large multi-phased  project to address numerous items identified in the 2019 Facility Condition Assessment report and have applied for numerous grants in addition to this funding request to make this project a reality.  The total estimated cost of the overall project is $525,000. The are seeking support from Parkland County for one phase of the project which has a total estimated cost of $50,281.35  . Additional funding sources have been applied for to cover the remainder of the $525,000 project.

 

Strategic Plan/Policy/Legal/Staff Implications:

Complete Communities

1.1 We offer a range of lifestyle choices, community services and other amenities to meet community needs.

 

Parks Recreation and Culture Master Plan Implementation Plan Recommendation 9.4 - Community Halls for the Future.

 

Policy C-RP03

 

Financial Impact:

Cost:   $25,000

Source of Funding: 2022 Budget